Lagos-Ibadan Expressway began in 2013, now 40% completed- Kuti

Lagos-Ibadan Expressway began in 2013, now 40% completed- Kuti
Written by Maritime First

The rehabilitation of the Lagos-Ibadan Expressway, a Federal Government project meant to result in Government’s partial closure Monday, of some section of the Berger axis, may have attained only 40 percent completion.

The Federal Controller of Works in Lagos, Mr Adedamola Kuti who confirmed the 40 per cent completion of a project began in 2013, with a completion date of 2017, noted that the date of delivery has now been shifted to 2021/2022, adding that the change of date was actually because the Muhammadu Buhari administration included some missing features.

He listed the additional features to include under passes, foot bridges, flyovers, toll plazas and road expansion.

Kuti said that the additional features shifted the completion date.

He added that the additional features made the completion level to still be at 40 per cent which it recorded months ago.

On the Ikorodu-Sagamu Road, expected to serve as an alternative route as construction work progresses on Lagos-Ibadan Expressway, Kuti said that the project was about 18 per cent completed.

He, however, added that critical sections of the highway likely to cause gridlock had been stabilised.

Also read:  6 die, 24 injured in auto crash on Lagos-Ibadan expressway

“The highway is about 18 per cent completed but I can tell you now for sure that there is great improvement on the road.

“What we did is, to first of all, tackle critical spots that cause traffic, and we are trying to link them up.,” he told NAN said.

He said that the ministry of Works, Housing and Power was working at night on some roads to ease gridlock.

“We have been fixing terrible but strategic roads. We are intervening here and there,’’ he said.

He noted that several road projects were abandoned in the past due to funding constraint, compelling the government to seek alternative sources of funding to fix more roads.

“A lot of projects were having difficulties getting appropriate funding but with other sources of funding, life has been brought  into one or two of our projects, and that is why you are seeing activities everywhere.

“Lagos-Ibadan Expressway is progressing, Apapa-Oshodi-Ojota-Oworonsoki Expressway Rehabilitation and Reconstruction project is on, and these are the critical roads that bind everybody, especially in Lagos, together,’’ he told NAN.

According to him, contractors are no longer being owed.

“Now, it is open-ended for contractors to collect whatever is the worth of work done in any project.”

 

 

 

About the author